By the time Gov. Tate Reeves told an audience of business executives last week that people “deserved answers” to their concerns about Mississippi’s data center boom, residents of Southaven had already spent more than a year trying to find them.
Reeves appeared by video at the Fortune 500 Innovation Forum in Detroit, Michigan, where he was asked to make the case for data centers in a state that is placing one of the country’s biggest bets on the AI economy but also where concerns about power, water, pollution and who will bear the costs are growing.
“There are legitimate answers to each and every one of those questions,” Reeves assured the gathering of leaders from the nation’s biggest companies, adding that his administration had “looked into” many of those issues.
Still, he provided no answers.
Instead, the outgoing governor blamed the nation’s foreign adversaries, such as China, for helping turn Americans against data centers through online misinformation, rather than the growing body of research indicating that communities hosting the enormous warehouses may be losing more than they get in return.
In Southaven, the questions are becoming harder to dismiss. A few days before Reeves spoke at the Fortune event, between 5,000 and 6,000 gallons of chemical coolant spilled at a local worksite used by Elon Musk’s data-center company, SpaceXAI. Four days before that, state regulators rejected residents’ challenge to an air permit for 41 permanent gas turbines that will power the 2.5 million-square-foot data center hub straddling the Mississippi-Tennessee border. Residents closest to the power station are slowly selling their homes to the company. In exchange, they can no longer join a class action lawsuit against the company. More than 20 residents have sold so far out among about 420 offers, according to DeSoto County property records.
The sequence captured the central contradiction of Mississippi’s artificial intelligence boom. Officials promote it in superlatives: the largest investment in state history, a generational opportunity, a source of jobs, tax revenue and cheaper power. But much of the information needed to test those promises remains hidden in confidential utility contracts and corporate nondisclosure agreements or emerges one permit and property record at a time. Nowhere has that pattern been more disruptive than in Southaven, where residents say they learn what is being built, and what it means for them, only after construction or government approvals are underway.
“There doesn’t seem to be any legitimate or believable answers to even the most basic questions,” said Shannon Samsa, a Southaven resident and founder of the Safe and Sound Coalition, a group pressing for environmental accountability. “Every solid answer that we have, we’ve had to obtain ourselves, through public records requests or other means.”
The coolant spill was just the latest example of the chaotic and frenzied pace of construction, where SpaceXAI has consistently built without permits and operated dozens of temporary methane gas turbines without permission.
The soon-to-be-operational permanent gas turbines covered by the latest approved permit will power Musk’s expanding data center complex on both sides of the Mississippi-Tennessee line.
To residents, the incidents are evidence of a powerful company moving at extraordinary speed while the public struggles to react to the full consequences before another decision becomes difficult to reverse.
When Reeves announced Musk’s $20 billion investment in January 2026, he described it as the largest economic-development project in Mississippi history, one that would “transform the region and bring amazing opportunities to its residents for generations.”
Southaven Mayor Darren Musselwhite called the development “game-changing,” pointing to a hundred jobs and millions of dollars in projected tax revenue, while rejecting accusations that the city concealed its dealings with the company or tolerated environmental violations.
“xAI has proven their commitment to being an outstanding corporate citizen in this regard in every possible way,” Musselwhite wrote in a January 2026 blog post. “Environmental sensitivity is at the forefront of this commitment as they go above and beyond required emission control requirements.”
Yet the public has been unable to test those reassurances. William Jerome, a Southaven alderman, told Scientific American that he signed a nondisclosure agreement a few days before the development was revealed, preventing him from discussing it publicly before the company’s announcement. Other officials involved with the project at the state and local level also signed such agreements. City records show that MZX Tech and the Musk Foundation gave a combined $3.23 million to support Southaven police during the same period that the city was approving agreements related to the development. Musselwhite rejected suggestions of a conflict and called the $1.38 million MZX donation an “unrelated transaction.” A subsequently-signed donation agreement contained a “No Quid Pro Quo” clause stating that nothing was expected in return.
The secrecy has been accompanied by a less formal absence of information and an indifferent attitude to resident concerns. Jason Haley, one of the lead plaintiffs in the class-action lawsuit over turbine noise and vibrations, said residents had asked Musselwhite to hold a city meeting but were told it would amount to “political theater.”
“He doesn’t keep us updated or informed,” Haley told The Mississippi Independent. “He doesn’t want to hear from his citizens about the harm this is causing.”
Haley says he is subjected to a loud, constant droning noise from the power plant 24/7, plus the daily sounds of construction. “There’s always something,” he said. “Today people’s houses were shaking in my neighborhood. Then I get a picture a few minutes later of a flame shooting way above the tree line. There’s no warning. There’s no heads-up to the citizens.”
That pattern has continued as SpaceXAI expands its data center footprint, which in the Memphis-Southaven area began with a facility designed to train its AI chatbot Grok. At the end of October, Musk disclosed two more Southaven data centers, called Gun Range and Spam after the properties’ former uses. One is being built on a former police and fire training ground; the other will replace a former food processing plant owned by the makers of SPAM meat.
The first public acknowledgment of Project SPAM appeared in state records on Oct. 16, 2026, when MDEQ granted a construction-stormwater permit to the company’s MZX Tech subsidiary. The project did not appear in the Southaven Board of Aldermen records reviewed by The Mississippi Independent before Musk’s announcement. The mayor and aldermen did not answer questions about its planning and construction approvals. By the time Musk told the public what the warehouse would become, work was underway.
“There has been zero meaningful engagement with our community, and I honestly doubt there ever will be,” Samsa said. She told The Mississippi Independent that she and others in the community were completely unaware of the new projects until they were announced. “It seems that they’d prefer to keep us in the dark to the fullest extent they can.”
After failing to obtain answers from state and local officials, Samsa’s organization has slowly gathered hundreds of documents that reveal glimpses of the truth about data centers in the community. One set of documents, for example, shows that two data center sites in Southaven consumed tens of millions of gallons of water in less than a year.
That lack of transparency is not confined to Southaven.
In 2024, Mississippi lawmakers passed legislation to accelerate utility construction for large data centers, reduce the Public Service Commission’s customary oversight, and allow certain terms of Entergy Mississippi’s agreement with Amazon to remain confidential. The public cannot see Amazon’s electricity rate or independently assess the protections Entergy says will prevent other customers from subsidizing its infrastructure.
Other data center companies were awarded similar deals.
Entergy says the data centers will lower bills by spreading costs across a larger customer base. It says its contracts include minimum payments, long terms and safeguards to protect existing customers if a large user leaves.
However, Entergy has backtracked on such promises in neighboring Louisiana, and a May report by Synapse Energy Economics, commissioned by two environmental organizations, reached a different conclusion. Using public filings, researchers estimated that residential customers had contributed about $38 million toward data-center-related investments by March 2026 and could contribute more than $74 million by year’s end. The report estimated the effect on an average monthly residential bill at as much as $10.60.
Entergy disputes those findings, saying bills are lower than they would have been without the new customers. The disagreement turns partly on what the data centers will pay over the life of the agreement and who picks up the remaining bill if the data centers leave or go bankrupt—precisely the terms the public cannot see.
In Southaven, residents face similar issues in identifying the truth. MDEQ allowed dozens of temporary natural-gas turbines to operate without air permits, accepting the company’s argument that equipment mounted on trailers qualified for a federal exemption intended for mobile sources. The decision also spared the temporary operation from the public process that accompanies an air permit. By the time residents challenged the arrangement, the turbines were running day and night.
A new federal permitting bill may make it far easier to obtain permission for major projects, including data centers and gas pipelines. The Senate passed its version of the bill. The House is expected to do the same in December.
On Oct. 30, 2026, U.S. District Judge Debra Brown rejected that interpretation while denying the company’s motion to dismiss a Clean Air Act lawsuit brought by the NAACP. She found that the turbines were not mobile sources under federal regulations and required permits. MDEQ responded that the order did not bind the agency because it was not a party to the case and noted that the litigation was continuing.
An independent study has since raised further questions about how much pollution residents in Southaven are being subjected to.
Using NASA satellite observations, scientists from the Massachusetts Institute of Technology and Carbon Mapper estimated in September that there was an average of 50 percent more nitrogen dioxide in the air within a six-mile radius of the Southaven plant from April through July 2026 than in the same months a year earlier. Researchers attributed the increase to the turbines. From March through August, they estimated, the temporary units released about 19 times as much nitrogen oxide pollution per hour as all 41 planned permanent turbines would emit with their required pollution controls.
A separate study by the International Energy Agency says that data centers will create 70 percent more carbon emissions by 2030.
MDEQ declined to comment on the research.
The November permit appeal concerned the permanent turbines, not the temporary ones. The Safe and Sound Coalition, the NAACP and Young, Gifted & Green argued that regulators had relied on inadequate pollution modeling, failed to require cleaner technology and omitted necessary emissions offsets. The company’s lawyers said the permit complied with state and federal law and had undergone extensive review.
After two days of testimony, the MDEQ permit board rejected the appeal. Agriculture Commissioner Andy Gipson cast the only dissenting vote, saying he had not received answers to all his questions.
“It is reprehensible that the permit board had a second chance to protect our community and still chose not to, especially after all the facts and evidence had been clearly laid out in front of them over the past two days,” Samsa said. “Whoever’s interests they are serving; it certainly doesn’t appear to be those of the people who actually live here.”
Board members deliberated in a closed executive session, another reminder of the limits residents face.
“So, we didn’t really get to hear any tangible reasoning or rationale for why they couldn’t so much as do the bare minimum of making adjustments to the permit to include stronger emissions controls to protect the folks living nearby,” Samsa said.
Other disclosures have arrived only after construction. State regulators found that work had begun at several company properties without the required stormwater permits. SpaceXAI noted in SEC filings that possible penalties could reach $6.1 million, though MDEQ has not confirmed that amount while enforcement proceedings remain pending. Weeks later came the coolant spill, and another round of questions about what had happened and who was watching.
The home purchases may give some residents a way out, for those who want out. They also present a stark version of the uncomfortable choices the project created: Remain beside a data center hub—the dangers of which are not fully known—or leave on terms offered by the company that built it.
Despite the resources of SpaceXAI and the entities backing it in Mississippi, some folks hold out hope for an equitable resolution.
“We are not going anywhere or backing down,” Samsa said. “We will continue advocating for our community until every last effort has been exhausted.”
Image: Grok search page (Getty Images)